How to Associate a Work Item with a Build

Use the Check In dialog box to associate work items with a check-in. This automatically associates these work items with the next build.

To associate a work item with a build
  1. Make code changes that you want to have included in the build and that will be associated with a work item.
  2. Check in the pending changes.
  3. In the Check In dialog box, click Work Items.
  4. Select the work item(s) you want to associate with this check-in.

All changesets that have occurred since the last successful build will be associated with the next build. After the next build, Team Build will list this changeset in the associated changesets for the build and will include the selected work item as being associated with the changeset.